Topic |
Detail |
---|---|
Total Project Budget |
$900,415 |
Funding From Revenue Bond |
$900,415 |
Funding From Other Sources | $0 |
Construction Start Date |
February 2017 - Admin Bldg. TBD - Pavilion |
Construction Completion Date |
July 2017 - Admin Bldg. TBD - Pavilion |
Topic | Detail |
---|---|
Total Project Budget |
$7,431,038 |
Funding From Revenue Bond |
$3,654,022 |
Funding From Other Sources |
$3,777,016 |
Construction Start Date |
May 2016 |
Construction Completion Date |
June 2017 |
Topic | Detail |
---|---|
Total Project Budget | $3,900,000 |
Funding From Revenue Bond | $1,700,000 |
Funding From Other Sources | $2,200,000 |
Construction Start Date | Varies |
Construction Completion Date | April 2017 |
Topic | Detail |
---|---|
Total Project Budget |
$438,000 |
Funding From Revenue Bond |
$350,000 |
Funding from other sources | $88,000 |
Construction Start Date |
November 2015 |
Construction Completion Date |
August 2016 |
Topic | Detail |
---|---|
Total Project Budget | $500,000 |
Funding From Revenue Bond | $250,000 |
Funding From Other Sources | $250,000 |
Construction Start Date | September 2015 |
Construction Completion Date | May 2016 |