Sewer Line Rehabiliation

The program will address priority areas which have the most infiltration and inflows as determined through visual observations and televising the collection system. Sanitary Sewer Evaluation Survey (SSES) are performed by staff, and recommendations for repairs are evaluated. This year, the project will continue in the areas which have high infiltration and inflows and/or lift stations operating below standards. Total wastewater flows to the treatment plant should be reduced through this aggressive infiltration and inflow control program, thereby reducing operational costs.

December 2018 - As of 11/28/2018 contractor has submitted the project binder with data associated with the annual project; currently under review reviewing. FY18 total sewer mains rehabilitated 14,972 LF and total cleaned and inspected 31,729. FY 2019 agenda item is being prepared and staff continues to develop the plan to identify basin areas for FY19 project.

November 2018 - As 10/31/2018 a total of 14,972 LF of sewer mains have been rehabilitated and 28,510 LF have been surveyed for FY2018. Vendor to submit post videos for review within the next two weeks. Staff is developing the plan to identify basin areas that will be rehabilitated in FY19.

October 2018 - As of 10/1/2018, waiting on submittals from the vendor for both Phase I and Phase II. To date the vendor has completed 98% of Phase I and Phase II work. 14,617 LF sewer mains have been rehabilitated of the 14,972 LF allocated for this project. Staff has begun the planning process that will supprot the program in FY19