ROADWAY PROJECTS UNDER DESIGN OR CONSTRUCTION

Roadway Projects Underdesign

Project 5: Extension of eastbound right turn lane on Miramar Parkway at Dykes Road.

SCOPE: Extend existing eastbound right turn lane from Miramar Parkway onto Dykes Road from 200’ to approximately 400’.

SCHEDULE: Design in 2020 and Construction in 2021.

Project 5 Pic
Project 6 Pic

Project 6: Additional southbound left turn lane on SW 145th Avenue.

SCOPE: Construct additional southbound left turn lane from SW 145th Avenue onto Miramar Parkway and necessary traffic signal modifications to accommodate the additional turn lane.

SCHEDULE: Design in 2020 and Construction in 2021.



Project 7: Intersection safety improvements at Miramar Parkway and Ivy Way.

SCOPE: Construct directional median to restrict northbound and southbound left turns and through movements from Ivy Way onto Miramar Pkwy.  Also, if warranted by Broward County, construct a mid-block pedestrian crossing just east of Ivy Way to go across Miramar Pkwy.

SCHEDULE: Design in 2020 and Construction in 2021.

Project 7 Pic

Project 8: Bass Creek Road connection west of SW 172nd Avenue


SCOPE: Construct new roadway connection of Bass Creek Road between SW 172nd Avenue and the north entrance to Sunset Falls development.

SCHEDULE: Design in 2020 and Construction in 2022

Project 8 Pic

Project 9: Pembroke Rd. and Miramar Parkway extension to US-27


SCOPE: Expand and extend Pembroke road to be a 4-lane divided roadway from Dykes Road to US-27; and Extend Miramar Parkway as a 2-lane roadway from SW 192th Terr. to Pembroke Road.  Including medians, landscape, lighting and buffer walls along residential areas.

SCHEDULE: Design in 2021 and Construction in 2023-2025

Project 9 - Pic